Salangana
PV Technical Guide - Roof, Thongs, Security

Installation of photovoltaic panels on the roof, connecting PV strings and DC/AC protection

This guide describes how to plan the layout of PV modules on a roof, how to connect panels into strings, where to use gPV fuses, SPD surge arresters, DC disconnectors, AC protection, grounding and fire protection elements.

string PVgPV fuseSPD DC/ACPV switchgearground

Safety: This is not a manual for an amateur

Technical Note: the PV installation operates on DC voltage, which cannot be turned off with a regular switch when the modules are lit. Installation, measurements and connection to the switchgear should be performed by a designer/installer with appropriate electrical qualifications. This material is for design understanding and quality control, not for performing live work yourself.

The greatest risks on the PV side are DC electric arc, incorrect polarization, too high string voltage at low temperature, poorly selected DC devices, lack of overvoltage protection, wrong cable route and incorrect passage of wires through the roof.

General diagram of a PV installation on the roof

The diagram below shows the typical order of elements. The actual design depends on the inverter, number of MPPTs, number of strings, presence of energy storage, lightning protection system and operator requirements.

PV MODULES ON THE ROOF └─ string 1: modules connected in series (+ / -) └─ string 2: modules connected in series (+ / -) ↓ DC solar cables, MC4-compatible connectors SWITCHBOARD/DC BOX ├─ gPV fuses for strings, if required ├─ DC disconnect switch / fire protection switch. DC if the project requires ├─ SPD DC surge arrester of the type appropriate to the installation └─ PE terminal / equalizing connections ↓ PV INVERTER / HYBRID INVERTER ↓ AC cable AC SWITCHBOARD ├─ AC circuit breaker ├─ RCD/RCBO if required by inverter type and design ├─ SPD AC surge arrester ├─ service disconnector └─ meter / connection point / main protection

3 visual schemes: MC4 string, parallel strings and hybrid system

To make the diagram understandable, it has been divided into four separate drawings. First, a single MC4 string is shown, then parallel string connection, and finally the full system with a hybrid inverter.

A single series string of PV panels connected with MC4 connectors
Rys. 1. String MC4. Single serial string: + module → - next module. The two extreme ends of the string go to the MPPT input of the inverter.
Two PV strings connected in parallel
Rys. 2. Parallel strings. Two strings connected in parallel: first, each row creates a separate string, then it is connected + z + and - z -. This connection increases the current.
General diagram of a PV installation with a hybrid inverter, battery, GRID and LOAD
Rys. 3. Overall hybrid diagram. Sample layout: PV string → DC protection → inverter; battery → BAT; network → GRID; reserve circuits → LOAD; AC protection, meter and grounding on the building side.
Order of reading diagrams: PV modules → MC4 string → parallel strings → hybrid inverter → GRID/LOAD/BATTERY.
Attention: the diagrams are illustrative. The actual selection of protections, cables, SPD, RCD, gPV fuses and grounding must result from the design, manufacturer's instructions and OSD requirements.

Explanation of terms from the hybrid schema

The following concepts apply only to the tổng thể hybrid scheme. Thanks to this, the reader understands what do the inverter ports and main blocks of the system mean without going into details tủ DC.

Term in the diagram Meaning What to watch out for?
PV / PV IN / DC1 / DC2 Inputs of photovoltaic panels to the inverter. They usually correspond to MPPT inputs. The strings must match the voltage and maximum current range of the MPPT input.
MPPT A system in the inverter that optimizes the operation of PV panels and searches for the point of maximum power. Different roof surfaces, different angles or different shading are usually better connected to separate MPPTs.
BAT / BATTERY Battery or energy storage port. You need to check the battery voltage, BMS type, CAN/RS485 communication and the inverter compatibility list.
GRID Connection of the inverter to the building/operator's power grid. Requires compliance with AC protection, meter, OSD conditions and energy export configuration.
LOAD Output to reserve circuits, i.e. backup/emergency circuits. It does not automatically power the entire house. Selected priority circuits are usually connected.
GEN Generator/chiller input if the inverter supports this mode. Requires configuration in accordance with the inverter manual. Not every hybrid inverter has the GEN function active.
Smart meter / energy meter A meter that measures the energy flow between the house, the inverter and the grid. It is needed for export control, auto consumption and the proper operation of many hybrid systems.
AC protection Protection on the AC side: miniature circuit breakers, RCD/RCBO, SPD AC and disconnectors. They are selected according to the inverter power, cable cross-sections, network layout and manufacturer's instructions.
PE/grounding Protective conductor and connection to earth. It is needed for protection against electric shock and proper operation of surge arresters.
The most important distinction: port GRID connects the inverter to the grid, and the port LOAD is used for backup circuits. These are not the same clamps and should not be confused.

Series and parallel connection of PV strings

These two diagrams show different functions. A single series string is used to increase the DC voltage, while parallel connection of several strings is used to increase the current at a similar operating voltage.

Connection type How does it connect? What's growing? What needs to be checked?
Privates + module → - next module String tension Inverter maximum DC voltage, MPPT range, Voc voltage at low temperature.
In parallel + stringu → + stringu and - stringu → - stringu Current of the entire system Maximum MPPT current, wire cross-section, connectors, combiner box and gPV fuses.
Important: Figure 1 shows the parallel connection of strings. First, each row of modules forms a separate serial string, and only then the ends of the strings are connected: plus with plus and minus with minus. This connection increases the current, so you need to check the MPPT limits, wiring and string protection.

Installation of PV panels on the roof – what needs to be designed?

Mechanical installation is as important as electrical installation. A poorly selected design may cause leaks, module stress, operation in the wind and service problems.

DesignRoof type

It is mounted differently on ceramic roof tiles, trapezoidal sheets, metal roofing tiles, felt, membranes and flat roofs.

LoadsWind and snow

The structure must be adapted to the wind/snow zone, roof angle, building height and hook/rail arrangement.

VentilationClearance behind the panel

The panel needs cooling from below. Too little clearance increases cell temperature and reduces production.

ServiceAccess and spacing

You need to leave space for access, roof edges, chimneys, roof windows, lightning protection system and cable passages.

Roof planning sequence

  1. Checking the load-bearing capacity of the roof and covering.
  2. Determining the slope: direction, angle, shading, obstacles.
  3. Drawing the modules while maintaining the edge zones and service accesses.
  4. Selection of mounting structure for covering and loads.
  5. Establishing DC cable routes to the inverter or DC box.
  6. Checking for collisions with the lightning protection system and ventilation elements.

How are PV panels connected into strings?

String PV is a chain of modules connected in series. In a series connection, the module voltages add up and the string current is similar to the current of a single module. The string must match the MPPT range and the maximum DC voltage of the inverter.

SerialTensions add up

10 modules of 40 V Vmpp give approximately 400 V Vmpp string.

In parallelThe currents add up

Two identical parallel strings give approximately 2× the current of one string.

MPPTSeparate areas apart

Different roof directions are usually better connected to separate MPPTs.

Patterns to check a string

The designer checks at least three things: maximum voltage in frost, operating voltage in heat and input current relative to the inverter.

Voc_string_cold = number_of_modules × Voc_of_module × temperature_correction_for_low_temperature Vmpp_string_hot = number_of_modules × Vmpp_module × temperature_correction_for_high_temperature I_string ≈ Module Imp; with parallel strings, the currents add up
Key: tension Voc_string_cold must not exceed the maximum DC voltage of the inverter or the rated voltage of the DC devices. This is one of the most important design mistakes when it comes to thongs.
Reminder: in a serial string, there is no "minus to minus" or "plus to plus" connection between subsequent modules. The correct series connection is always plus of one module to minus of the next module.

What not to mix in one string?

  • modules with different power and current-voltage parameters;
  • modules facing different directions if they work on one MPPT;
  • modules from different areas with strongly different shading;
  • old and new modules without converting string parameters.

DC switchgear: string fuses, DC SPD and switch disconnector

The DC side of a PV installation requires devices designed for DC current and PV voltages. They must not be replaced with random AC units.

ElementFunctionWhat to watch out for?
gPV string fuseIt protects the string against reverse current from other parallel strings.The selection depends on the Isc of the module, the number of parallel strings and the maximum module protection current from the data sheet.
DC fuse baseEnables installation of the gPV insert.It must be rated for the appropriate DC PV voltage and short-circuit current.
DC isolating switchEnables safe disconnection of the DC side from the inverter.Must have DC PV category and voltage; it is not an ordinary AC switch.
SPD DCLimits overvoltages on the side of panels and DC cables.The type, voltage Ucpv and connection system for the installation and LPS are selected.
PE terminal / potential equalizationIt connects the structure, frames and devices with the protective system.Grounding conductors must have the correct cross-section and routing.
DC housingProtects equipment against dust, moisture and touch.The IP rating, UV resistance and location must match the installation conditions.

When to use string fuses?

A string fuse is needed when reverse current from other parallel strings may flow through a damaged string or when it is required by the project, standard, inverter or module data sheet. In systems with multiple parallel strings, each string is typically secured separately.

In practice, the selection of the gPV insert depends on the short-circuit current of the module Isc and the permissible maximum protection of the module from the data sheet.

Design principle: For string protection, a range above the module operating/short-circuit current and below the maximum protection allowed by the module manufacturer is often used. The exact value must be calculated by the designer based on the module data and the standard.

Example DC box layout

STRING 1 + ── gPV fuse + ┐ STRING 2 + ── gPV fuse + ├── DC switch ── SPD DC ── MPPT input of the inverter + STRING 3 + ── gPV fuse + ┘ STRING 1 - ── gPV fuse - ┐ STRING 2 - ── gPV fuse - ├── DC switch ── SPD DC ── MPPT input of the inverter - STRING 3 - ── gPV fuse - ┘ PE / earthing ───────────────── SPD DC / structure / equipotential bonding

AC switchboard: circuit breakers, RCD, SPD and inverter connection

On the AC side, the inverter is an energy source connected to the building's installation. The AC switchgear must provide cable protection, inverter disconnection, overvoltage protection and compliance with operator requirements.

Element ACFunctionDesign notes
AC circuit breakerProtects the inverter AC cable against overload and short circuit.It depends on the inverter power, current, cable cross-section and installation method.
AC service disconnectAllows you to disconnect the inverter on the AC side.It should be accessible and clearly marked.
RCD/RCBOResidual current protection if required by inverter design and type.The type of RCD depends on the inverter instructions and possible DC components of the leakage current.
SPD ACSurge protection on the mains side.The choice of type depends on the lightning protection system, network layout and risk assessment.
Meter/pre-meter protectionSettlement point and connection power limits.Requires compliance with connection conditions and DSO documentation.
Important: on the AC side, equipment is not selected by eye. Wire cross-section, voltage drop, inverter power, existing installation protection and operator conditions must be checked together.

Lightning protection, grounding and SPD surge arresters

Installing PV on the roof changes the situation of the building in terms of overvoltages and equipotential bonding. You need to check whether the building has an external LPS lightning protection system, what the separation distance is and how the DC cables are routed.

SPD DC i SPD AC

  • SPD DC is mounted on the side of the PV cables, selecting the voltage Ucpv to the maximum string tension.
  • SPD AC is installed on the network side of the inverter, depending on the switchgear and the building's overvoltage protection system.
  • In a building with a lightning protection system or an increased risk of overvoltage, the design may require a type 1+2 SPD instead of type 2 only.
  • SPD connections to PE should be as short as possible and carried out in accordance with the manufacturer's instructions.

Grounding of structures and panel frames

The mounting structure, module frames and metal elements should be equipped with equipotential bonding according to the design. It is especially important to use appropriate clamps, washers and cables intended for outdoor use.

Do not shorten surge protection: Grounding the structure itself does not replace SPD, and SPD does not replace proper grounding and equipotential bonding. These elements work as a system.

Fire protection requirements, markings and cable routes

In Poland, PV installations with a power greater than 6.5 kW require additional fire protection procedures. The design should be agreed with a fire protection expert, and after the installation is completed, the appropriate State Fire Service authorities should be notified in accordance with current regulations.

What should be marked?

  • presence of a photovoltaic installation on the building;
  • DC cable routes if relevant to rescue operations;
  • location of the inverter and DC/AC switchboards;
  • main AC and DC disconnection points;
  • installation diagram available to the user and service.

DC cable routes

DC cables should be routed to reduce the risk of mechanical damage, overheating, DC arcing and disruption to service operations. Avoid sharp edges, loose loops, water collection areas and unnecessarily long routes inside the building.

Measurements and acceptance of PV installations

After installation, the installation should undergo measurements and documentation control. This is not a formality - errors on the DC side may not be immediately visible, but increase the risk of failure or fire.

ControlWhat to check?Why?
Thong polarizationCorrect plus/minus before connecting the inverter.Incorrect polarity may damage the inverter or DC devices.
Voc of each stringOpen circuit voltage comparison with design.Detects wrong number of modules or wrong connection.
Thong currentComparison of parallel/string currents.Detects shading, connection errors or damaged modules.
Insulation resistanceInsulation of DC cables to ground.Important for the safety and operation of the inverter.
PE continuityEqualizing connections of structures and devices.Required for protection against electric shock and overvoltage.
SPD test and markingsStatus of SPD indicators, circuit description, diagrams.Facilitates service and rescue operations.

Technical checklist before acceptance

Modules arranged in accordance with the design, without collisions with windows, chimney, LPS and service zones.
The structure is selected for the roof covering, wind and snow loads.
Number of modules in a string checked for maximum voltage at low temperature.
Strings assigned to MPPT according to the roof direction and shading.
DC solar cables run without sharp edges, loose loops and risk of damage.
Connectors compatible, properly crimped and not accidentally connected between different manufacturers' systems.
gPV fuses used where the number of parallel strings and the design require it.
SPD DC and SPD AC selected for voltage, network layout, LPS and overvoltage risk assessment.
DC/AC switches available, described and compliant with the operating category.
Equalization connections and grounding made in accordance with the design.
The AC switchgear has the appropriate circuit breaker, any RCD/RCBO, SPD and descriptions.
Measurements were made: polarization, Voc, string currents, insulation, PE continuity.
For installations above 6.5 kW, fire protection obligations, documentation and notification of the State Fire Service were checked.

Technical and normative sources

When designing and accepting, use current standards, instructions from module/inverter manufacturers and the requirements of the local DSO. Standards and documents regarding PV installations, electric shock protection, overvoltage protection, DC disconnection and fire protection procedures are particularly important.

  • IEC 60364-7-712 – requirements for electrical installations of PV systems.
  • IEC 62548 – design requirements for PV generators/systems.
  • PN-EN IEC 61643-31 – surge arresters for DC photovoltaic applications.
  • PV module installation instructions and module catalog card.
  • Inverter installation instructions and list of acceptable protections.
  • OSD requirements and fire protection documentation. for installations above 6.5 kW.

FAQ

Does every PV string have to have a fuse?

Not always. A string fuse is needed when dangerous reverse current from other parallel strings may occur or is required by a design, standard, module card or inverter. For a single string on MPPT, a separate gPV insert is often not used, but the decision must be confirmed by the design.

Can I use a regular AC fuse on the DC side?

NO. The DC PV side requires devices designed for DC PV and the appropriate voltage. The DC arc is more difficult to extinguish than in AC circuits.

What does SPD type 1+2 in PV mean?

This is a surge arrester that combines the function of protection against surge current and overvoltage. May be required in installations with external lightning protection or where there is an increased risk of overvoltage. The selection depends on the project.

Can DC cables run through the attic?

They can if the design includes a safe route, mechanical protection, markings and fire protection requirements. Unnecessarily long DC paths inside the building should be limited.

How to choose the number of modules in a string?

You need to check the Voc voltage at the lowest temperature, the Vmpp voltage at the high temperature, the MPPT range of the inverter, the input current and the module parameters. The number of panels is not selected only by dividing the installation power by the module power.